Five key trends reshaping clean energy deal complexity

Read Time
0 min
Veridue logo centred above a sage-green solar-panel engineering blueprint.

European renewable energy deals are becoming increasingly complex. Scarce grid capacity and weaker revenues during peak generation hours are putting pressure on valuations. In Spain, for example, wholesale electricity prices were negative for 17% of hours in the first half of 2026. PPA buyers are increasingly seeking to share negative-price risk with generators. Some newer government CfDs also suspend generation-linked support during negative-price periods, and we expect such exclusions to become more widespread across Europe. More frequent negative-price periods would therefore erode the revenue protection these contracts provide to wind and, in particular, solar assets.

Revenue pressures are driving greater use of storage to improve renewable projects’ revenue profiles. Meanwhile, new data centres are creating offtake opportunities that can involve more demanding delivery commitments. These arrangements also shape financing: merchant batteries may offer higher returns but require more equity, while contracted revenues can support greater borrowing in exchange for limiting some of that upside. Investors therefore have more ways to tailor deals to their risk appetite, but choosing between them requires closer analysis of contractual obligations, debt capacity and equity requirements.

Looking ahead to 2027, five trends are reshaping how investors value renewable assets, structure acquisitions and fund development.

1. Grid scarcity is changing how connection rights are valued

Scarce capacity and long grid connection queues mean that, from an investor’s perspective, acquiring an existing project can represent a faster route to market. “Acquisitions are increasingly becoming grid rights transactions disguised as renewable energy deals,” says Melchior Villet, founder’s associate at Veridue.

The value of those rights depends on the connection date and whether access is firm or non-firm. At UK Power Networks, over 313 MW of flexible connection capacity went live in 2025/26, compared with over 194 MW the previous year. We expect uptake to grow as developers accept restrictions on output in exchange for earlier grid access. For buyers, this makes the premium paid for an earlier connection increasingly dependent on the terms of curtailment: how much revenue starting sooner brings, how much restrictions could remove, and whether any compensation applies.

Planned grid works can change an asset’s operating conditions after acquisition. Reinforcement may ease export restrictions, but delays can prolong them. If the buyer is paying for additional export capacity expected from grid upgrades, part of the purchase price could be payable only once that capacity becomes available.

Grid connection reforms are also changing which projects remain in the development pipeline. In Great Britain, projects are now prioritised according to their readiness and alignment with national energy targets. Meanwhile, Romania’s May 2026 reforms increased the grid connection guarantee for new generation projects with approved export capacity above 1 MW from 5% to 20% of the connection tariff, subject to transitional exemptions. These measures make holding speculative capacity more costly and favour developers able to demonstrate progress and commit funding.

As these reforms take effect, we expect connection queues to become a more credible guide to future development. That should give buyers a stronger basis for assessing how neighbouring generation, storage and demand projects could affect local congestion. The premium for an earlier connection should reflect both the revenues earned by starting sooner and the operating conditions the asset will face as neighbouring projects connect and the grid develops.

2. Co-located storage is changing the investment case for solar

Weak solar capture prices are strengthening the case for adding batteries to both development projects and operating assets. Batteries can benefit from the trough hours that undermine solar revenues, storing electricity for delivery during peak hours. This can provide a partial hedge against low solar capture prices.

Spain is a particularly topical market: solar’s capture rate fell from around 102% of the average wholesale price in 2019 to 56% in 2025. This pressure on solar revenues, alongside shorter permitting timelines for adding batteries to eligible renewable projects, strengthens the case for co-location. LevelTen reported that new PPA offers combining renewable generation with storage more than doubled year on year in Q2 2026, as developers use storage to offer buyers more valuable delivery profiles and secure prices that make projects financeable.

“Given the low prices of standalone solar PV PPAs, delivery profiles closer to baseload can allow investors to secure better contracted revenues and, in turn, support higher gearing and reduce the cost of capital,” says Quentin Pletinckx, commercial lead at Veridue.

However, the expansion of storage is already putting pressure on ancillary-service revenues. In France, average upward aFRR reserve capacity prices fell 55% between January 2025 and January 2026 as more capacity competed to meet the same requirement. Rising BESS penetration can also cannibalise arbitrage revenues as more assets compete to monetise the same price spreads. Continued renewable deployment can counteract this erosion of arbitrage revenues by sustaining price spreads. We therefore expect the value of adding storage to solar to diverge across European markets: where renewable deployment sustains demand for flexibility, co-location can continue to improve solar capture prices and support more valuable PPA structures; where storage deployment outpaces that demand, revenue cannibalisation is likely to constrain the uplift.

3. Data centres are changing how energy sites are valued

The IEA projects European data-centre electricity demand to increase by around 70% between 2024 and 2030 in its base case. Connection delays in established markets have led investors to target regions with more available grid capacity. This creates a potential additional source of value for energy sites capable of accommodating large new loads.

“Developers are also reassessing their strongest generation and storage projects as potential data-centre sites,” says Daniel Csonth, founder of Veridue. Existing infrastructure can offer a head start, but export rights do not automatically confer import capacity, and nearby renewable generation does not guarantee continuous supply. The opportunity depends on how much import capacity can be secured and when, alongside fibre connectivity, cooling requirements and planning constraints. Beyond potential site sales, data-centre development also creates opportunities for energy asset owners to secure new offtake partners.

However, connection enquiries can substantially overstate the demand progressing towards delivery. Fingrid reported more than 50 GW of data-centre connection enquiries at the end of 2025; by mid-October 2026, projects with signed connection agreements represented just over 5 GW of planned capacity, including distribution-connected projects. Valuations that treat these enquiries as future PPA demand risk overstating both the scale of the opportunity and how quickly it will materialise.

Connection policies are also creating a more direct role for energy developers. In Ireland, new data centres requesting at least 10 MVA must provide onsite or electrically proximate dispatchable generation or storage covering their import capacity on a de-rated basis. New data centres at or above the policy’s 1 MVA threshold must also meet at least 80% of annual demand with additional Irish renewable generation within six years of energisation. This gives renewable and storage developers a role in enabling data-centre connections and expansion, creating scope for partnerships agreed earlier in the development process.

We expect more renewable deals to involve offtake agreements whose value depends on the delivery schedule of a separate data-centre project. If the start of contracted offtake can be postponed until the data centre opens, the generator may have to sell its output elsewhere, potentially at lower prices. Conversely, delays to essential power infrastructure can prevent the data centre from operating. Acquisition and power agreements must establish who bears liability for each delay, when offtake and payment obligations begin, and what compensation or termination rights apply. For renewable investors, the conditions governing the start of contracted offtake could become as important in negotiations as the headline PPA price.

4. Changing development rules are complicating cross-border portfolio assessments

The large renewable and storage pipelines built up in recent years have overwhelmed connection queues, prompting reforms to prioritise projects capable of progressing. Authorities are seeking to accelerate viable developments while tightening the requirements for securing and retaining grid capacity. This is changing the sequence of development milestones and the evidence developers must provide to advance.

These changes are taking different forms across markets. Germany’s transmission operators now assess storage and large-consumer applications through a maturity-based process, preserving existing connection commitments but requiring pending applications to be updated and resubmitted. Alongside grid reforms, planning requirements are also changing: from January 2027, new applicants using Poland’s WZ zoning-decision route must secure rights to use the land for construction before applying, while earlier proceedings retain the previous rules. Such changes affect both the work remaining and the order in which developers must commit resources.

For investors assessing pan-European portfolios in 2027, we expect an additional complication to be navigating several changing regimes within one transaction. A project’s reported development stage may remain unchanged even though its route to the next milestone has changed. “Developers define milestones differently, meaning investors need to understand what has actually been secured and what remains before a project can be built,” says Daniel Csonth, founder of Veridue.

A common assessment framework must therefore translate the rules applying to each project into realistic remaining costs and delivery dates. Where new requirements bring land commitments forward, require applications to be reassessed or introduce additional deadlines, the acquisition model must reflect those consequences. Otherwise, a portfolio can appear closer to construction—and less costly to complete—than the obligations inherited by its buyer justify.

5. Development pipelines face tougher tests of deliverability

A development platform can hold credible projects without having the capital or delivery capacity to advance them simultaneously. Several projects reaching construction together can create overlapping demands for equity, equipment and experienced staff. For buyers, the investment case therefore depends on whether the platform can deliver the combined programme within the budget and timetable assumed in its valuation.

“Even a modest increase in borrowing costs can make a project unviable for investors by increasing debt-service costs and limiting achievable gearing, which can raise the overall cost of capital,” says Quentin Pletinckx, commercial lead at Veridue. Within a fixed platform budget, greater equity requirements per project can reduce the number funded concurrently. Where the platform also relies on project sales or refinancing to fund subsequent developments, a delay in one transaction can hold back the wider pipeline.

Procurement constraints can reinforce these dependencies. The IEA reported in 2025 that lead times for large power transformers had almost doubled since 2021, reaching up to four years. Projects reliant on the same substation upgrade or equipment delivery can consequently slip together. Securing equipment earlier may protect the delivery schedule, but it can also bring deposits and other commitments forward, increasing the capital required before projects generate revenue.

In 2027, we expect platform assessments to place greater weight on peak funding requirements and the number of projects the team can execute concurrently. Acquisition models should reflect a sequenced delivery programme, including the additional equity, staffing and procurement commitments needed to achieve it. If the buyer cannot fund that programme, some projects must move back—and the valuation must reflect the later revenues and additional holding costs.

Delivery and returns must be assessed together

Looking ahead to 2027, five trends are reshaping how investors value renewable assets, structure acquisitions and fund development. Securing earlier grid access may mean accepting output restrictions; obtaining stronger contracted revenues may require storage investment or commitments linked to another project’s delivery. The value of these opportunities depends on whether the buyer has the capital, capabilities and risk appetite to realise them.

“Diligence should help investors decide which assets to buy and how they fit the investment thesis, including the risks and capital requirements that could affect returns,” says Quentin Pletinckx, commercial lead at Veridue. That assessment should shape the acquisition price, the timing of payments and the obligations each party retains. Where returns depend on further approvals, infrastructure or counterparties, the deal must establish who funds the remaining work and who bears the consequences if delivery slips.

For developers, demonstrating those dependencies—and a credible plan to manage them—will help buyers distinguish achievable upside from potential that still requires substantial investment. For investors, the opportunity in 2027 is to select and structure deals around the risks they are equipped to carry, with the acquisition model reflecting the full capital and time required to earn the projected return.